La Glâne training centre

Goal
As part of the renovation of the Glâne training centre, a temporary school will host more than 600 students. This building, located on an old sports field, will consist of 246 shipping containers and will contain 27 classrooms, as well as changing rooms and stairways for a period of 36 months. Our temporary solution combines speed and comfort for students. In fact, fresh air will be guaranteed inside the classrooms and students will also have science laboratories, visual arts and exam rooms. Some classrooms will even be equipped with connected tablets and interactive whiteboards which will then be moved to the new school building.

Material
246 containers which include classrooms, changing rooms, stairs, science laboratories, visual arts and exam rooms.

Duration
The temporary school will be present for a period of 36 months. Delivery of the project is scheduled for August 2021.